Processing a Job:

  • Quote is reviewed to ensure current pricing
  • Drawings are reviewed to ensure current revisions and completeness
  • Packet (P.O., RFQ, Quote Audit & Drawings) goes to Production Manager
  • Production Manager creates job, sends customer an order acknowledgement and prints traveler with routing info.
  • Traveler & drawings go to Engineer for review and programming
  • Traveler is released to shop floor for production

Checklist for RFQ (same as sending job):

There are some key elements that are needed to aid us in this process.  We use a "Request For Quote" form.  This form is used as a checklist to ensure that we have all the necessary information to quote and/or manufacture your parts.  The following is an example of the information we are required to gather from you.

  1. Part number.
  2. Quantity.
  3. Do you require 1st articles?
  4. Requested lead-time or delivery date.
  5. Readable drawing.
  6. Do we have the correct revision level?
  7. Can you supply a computer aided drawing (CAD) file? (example: .dwg or .dxf)
  8. Part description.
  9. Tolerances for laser cutting, fabricating, bending, shearing. (dimensional and angular.)
  10. Does the part need to be deburred?
  11. Do tabs or micro joints need to be removed?
  12. Customer supplied material?  (If so, we need an inspection criteria form filled out and faxed back, or your PO needs to include details of material supplied, this enables us to verify that we have received all the necessary and correct materials needed to proceed with production.)
  13. Do you require material certification?
  14. Weld details if applicable.
  15. Finish. (raw, plated, painted, etc.)
  16. Packaging requirements or policy.
  17. Do you accept over or under shipments?  If so, what percentage?

This seems like a lot of information, but it is essential in order to assure that we satisfy you as a customer. Getting all this information up front will make your quote, and/or job move through our system with speed and accuracy, we call this speed to market. With the exception of 1st article, lead-time, computer-generated file, customer supplied material, and acceptable shipment quantities, all of these questions should be answered with a complete drawing. Thank you in advance for giving this checklist your undivided attention. If you have any questions, please contact any of our staff for further explanation. We are confident this will make for a smooth, trouble free relationship, and allow us to provide you with a quality product made to your specifications.

Drawing Formats Accepted:

  • .dwg
  • .dxf
  • .igs
  • .sat
  • .srf
  • .step
  • .stl
  • .stp